Objective
Increase the overall stormwater capacity of the Arboretum Waterway – the largest part of the campus’s stormwater infrastructure – by 6 acre-feet and replace most of the concrete perimeter with earthen banks, native trees, shrubs, and understory plants. Narrow sections of the waterway to facilitate faster water movement. Incorporate floodplain benches and emergent marsh plantings to mimic natural wetland habitats.
Metric
Benefiting from a $5.4M grant from the California Natural Resources Agency and a $2.5M matching grant from UC Davis, complete the construction project on budget and before November 2025.